Ex-Situ Groundwater Bioremediation
KwaZulu Natal Province, South Africa | Underground void water remediation plant | 2024 – Present
Project Details
Sector: Power Generation / Coal Mining
Main Technology: Biological Sulphate Reduction (BSR)
Duration: Oct 2024 – Sep 2025 (Pilot)
Targeted Contaminants: SO4, Acidity, associated metals (Fe, etc.)
Scale: Containerised pilot → full-scale design
Project Timeline
Oct 2024
Site Scoping
Jan 2025
Pilot Installation
Mar–Aug 2025
Full Operations
Sept 2025
Decommissioning
2025+
Full-Scale Design
The Challenge
A national power utility operating a coal-fired power station in Mpumalanga faced persistent acid mine drainage and elevated sulphate concentrations from an adjacent colliery. Conventional chemical treatment carried prohibitive long-term costs and generated large chemical sludge volumes. The utility required a sustainable, biologically driven alternative capable of operating at scale with minimal chemical input – and needed pilot-scale proof before committing to a full facility.
Our Approach
iWater designed and deployed a containerised biological sulphate reduction (BSR) pilot plant, progressing from scoping through to full operational demonstration over 10 months.
- Comprehensive site scoping and water characterisation to define feed chemistry and design parameters
- Custom bioreactor system with PLC-controlled dosing, mixing tanks, and integrated monitoring
- Phased installation with iterative refinements based on operational feedback and performance data
- 9 technical deliverables from scoping through to upscale design, with international engineering review
- Safe decommissioning with bacterial communities preserved in bioreactors for future re-activation
- Deliverable: 5 000 / day of treated acid mine drainage (AMD) water to release quality set out in water use license (WUL) after gabion and wetland polishing system
The Results
The pilot plant successfully demonstrated biological sulphate reduction under real site conditions, generating validated data to support full-scale facility design.
| Parameter | Result |
|---|---|
| Fe reduction | 99% (27.5 → 0.33 mg/L) |
| SO4 reduction | 87% (1 978 → 254 mg/L) |
| Alkalinity Generation | +336% (188 → 820 mg/L) |
| Average daily volume | > 5 000 ℓ |